CONSTRUCTION OF ABIOLA –ONIJEMO LINK ROAD WITH BRIDGE IN IFAKO-IJAIYE LGA

To prevent flooding, improve the environmental status of the communities, provide an effective by-pass to traffic gridlocks and a strategic link from College Road through Ajayi Street, Ogba to Aruna/Obawole/Iju-Ishaga in Ifako-Ijaiye Local Government Area and Ojodu Local Government, the project is expected to Improve interconnectivity of roads within the axis.


So far we have completed the Piling works, 28 piles+1Relief Pile and the Pile Cap, Piers and Pier Caps Completed as well as the Abutment Walls are all completed
Installation of Precast Beam Girders On-Going

Overall, the project (Bridge and Road works) is currently at 62% completion and the contractor promised to deliver the project by May 2024